  1. Task
    Rate
    Qty
    Amount

    Solar Panels

    Longi Himox6 580watt

    PKR24,070
    18
    PKR433,260
  2. Installation/Wire/Breaker 

    6mm Tin coated

    Tomzan

    PKR205,000
    1
    PKR205,000
  3. Solar Inverter

    Growatt 10Kw

    PKR285,000
    1
    PKR285,000
  4. Earthing & Boring 

    PKR50,000
    1
    PKR50,000
  5. Lightening Arrestor with Earthing wire and 100 amp breaker and db box

    PKR50,000
    1
    PKR50,000
  6. Net Metering with Complete file 

    PKR120,000
    1
    PKR120,000
  7. Elevated Structure for 18 panels

    PKR230,000
    1
    PKR230,000
  8. Transporation Charges

    PKR10,000
    1
    PKR10,000
Subtotal PKR1,383,260.00
Total PKR1,383,260.00

Notes

    • Payment Account:
    •  Alfalah Bank
    • Account title: Beart and Gibson
    • Account no. 0570-1008737668
    • IBAN: PK92ALFH0570001008737668.
    • MCB Bank
    • Account title : Beart and Gibson
    • Account no. 0504526871002959
    • IBAN:PK21MUCB0504526871002959
    • Meezan Bank
    • Account Title: Abdul Waheed
    • Account no: 11490104599485
    • IBAN: PK52MEZN0011490104599485
    • United Bank Limited
    • Account Title: Beart and Gibson
    • Account no: 11490104599485
    • IBAN: PK24UNIL0109000308830509
    • Payment Terms:
    • 75% payment upfront.
    • 15% at the time of delivery.
    • 10% at completion.
    • .
    • Note:
    • Structure cost may depend on survey.
    • Installation within 5 working days after receiving payment.
    • Net-metering depends on government department policies.
    • This quotation is valid for 48hrs from the mentioned date.
    • PLEASE NOTE WE DO NOT TAKE ANY RESPONSIBILITY FOR ANY LOSS OR DAMAGE UNTIL WE HAVE RECEIVED THE PAYMENT IN OUR COMPANY BANK ACCOUNT.
Updated
April 29, 2024 @ 11:25 am

Estimate updated by beartandgibsonenergy.

Updated
April 29, 2024 @ 11:26 am

Estimate updated by beartandgibsonenergy.

Updated
April 29, 2024 @ 11:28 am

Estimate updated by beartandgibsonenergy.

Updated
April 29, 2024 @ 11:37 am

Estimate updated by beartandgibsonenergy.

Updated
April 29, 2024 @ 11:37 am

Estimate updated by beartandgibsonenergy.